NW Barstow Street Project

Project Update July 14, 2017
  

 

This week the contractor finished all of the sidewalk, ADA ramps, and driveway approaches excluding Lemira Avenue. On Friday (7/14) they began prepping the roadway for pouring early next week. The current schedule is Tuesday morning July 18th at 6:00 A.M. there will be no vehicular access allowed on NW Barstow St. To help reduce the overall impact to the residents, it is the contractor’s intention to pour the entire road in 1 day, except they will provide gaps in the pavement at both Prospect Avenue and Bidwell Avenue so access can be maintained to homes/business East of NW Barstow. The Contractor will begin the concrete pour at 6:00 A.M. Tuesday and will need to be saw cutting the pavement possibly as late as midnight. We do apologize in advance for the noise. Following the pour the concrete will need 4 days to cure before opening the road. NW Barstow will be back open to traffic by noon July 22nd. All dates are weather dependent.

 

Parking

From July 11th – July 18th at 6:00 A.M. it is ok to park on NW Barstow on the West side of the road or any adjacent side road overnight (without a parking permit, please follow any parking restrictions). It is still ok to park on any adjacent side road overnight (without a parking permit) until July 22nd.

 

The upper City Hall parking lot (off of Buena Vista Ave.) is also available (without a parking permit) from 5:00 P.M. till 7:30 A.M. Monday through Friday, and weekends from 5:00 P.M. Friday until 7:30 A.M. Monday until the road is reopened to residents.

 

 

Any further questions feel free to contact me. 

Project Contact Information
Craig Ausen, P.E.
Project Engineer
City of Waukesha - Engineering Division
130 Delafield St. Waukesha, WI 53188
O: (262) 524-3589
C: (262) 349-6516
 

Barstow update july 7