Proposed Fire Station No. 3 and Police Substation

Project Update: July 21, 2017

    

 

 

This week the masonry walls in the apparatus bay were completed.  Framing began on the PD side of the building. Today the apparatus bay concrete floors were poured.

 

Next week the walls and framing will continue.  More floors will be poured and electrical will continue to be roughed in.  The site restoration should continue with topsoil and seed.


     
  

 

Framing 2
The Westerly drive into the church has been closed to church traffic and is being used for construction traffic. 

The Sanitary Sewer extension and Construction of the Access Road to the Station, across the front of St. John Newmann's property has been awarded to Musson Brothers. 
 
Contact Information:

Katie Jelacic, P.E.
Project Engineer
262-524-3587
262-349-6511 (c)
kjelacic@waukesha-wi.gov
Apparatus Floor pour FD